Anfield Stadium Development
Washington, DC
Project Overview
RSF: 15,000
Project Type: Base Building Development
Project Team
Developer: Anfield Stadium, LLC Architect: Collective
Construction: Winmar Construction MEP Engineer: Century Engineering Structural Engineer: MGV Engineering Civil Engineer: Bohler
Project Features
​
-
Vertical and Horizontal Green roofing Systems to meet GAR requirements.
​
-
Orange Barrel Media digital display.
​​
-
Flexibly designed for up to 4 retail tenants.
​​
-
​Lot purchased with an existing approved permit set
​​
-
Relocated vault location and install a new vault due to size of the required transformer.
Highlighted Services
​
-
Development management.
​
-
Worked with zoning attorneys and dry utility expeditors.
​
-
Coordinated with DCRA, DOEE, DDOT, ANC, HPRB, and all utilities.
​​
-
Worked with the design team to identify design modifications that could be approved by the Office of the Zoning Administrator — avoiding a Zoning Commission hearing and saving the client an estimated 3–6 months of schedule delay.
-
Provided cost benefit analysis of potential redesign vs moving forward with the existing approved permit set.
​
-
Relocated vault location and install a new vault due to size of the required transformer.
Successful Results
​
-
Accelerated schedule.
​
-
LEED Certification.​
​
-
Created and guided client through multiple tenant work letters.
​
-
Created flexible space meeting all tenant requirements.
​​
-
Maintained budget and schedule throughout global pandemic and local unrest.
​
-
Accelerated schedule and delivered $1.7M+ in cost savings through value engineering and redesign within existing zoning-approved plans — avoiding a Zoning Commission hearing and saving the client an estimated 3–6 months of schedule delay.